Avoca crossing points
Published on 23 June 2021
Crossing points in High Street, Avoca
Work is underway for the construction of four pedestrian crossings on High Street Avoca. Works commenced today (28/6) on the west side at Duke St outstand, contractors Fulton Hogan will continue along the west side until all four are complete then do all four systematically along the east side; then do the central median footpath links.
Traffic is down to one lane at 40kmh, we thank you for driving safely.
Construction is expected to last about four-five weeks, weather dependent.